The Indonesian State Electricity Company aims to implement a sustainable hydropower programme to meet Indonesia’s rising electricity demand.

Challenge

The Indonesian State Electricity Company, PT. PLN (Persero) aims to implement a sustainable hydropower programme to meet Indonesia’s rising electricity demand by rehabilitating existing and constructing new hydropower plants. PLN chose the Nua small hydropower plant (SHPP) project as one component of the programme. Tractebel Engineering GmbH and their entity Tractebel Hydroprojekt GmbH, in association with Indonesian Consultant PT Connusa Energindo, were appointed by PLN and KfW Development Bank to review, assess and update the existing feasibility study.

In order to improve the feasibility of the project and increase the energy production, it was found that the original plant design needed to be revised and new alternatives proposed.

Sites being often remote and hydrological, and limited in geological and topographic data, have created major challenges to fulfil the task and to provide reliable results in the early stage of the project.

Ground survey topographical map - Indonesia Worldem case study

Our Solution

Digital Terrain Models (DTM) were used to validate the ground survey topographical map. Furthermore, this solution offered a reliable and very accurate database essential to assess the feasibility study. It was used to estimate the hydraulic head and the energy production of the SHPP, to locate the main project components (e.g. weir, powerhouse), to assess the layout and the type of waterways and to estimate the catchment area. The use of DTM is essential to the planning process and the decision-making process.

Airbus WorldDEM is perfect to cover a global area and suited the need to cover a larger area. The plausibility of the ground survey topographical map can be checked with the WorldDEM and vice versa. As a result, Tractebel were able to confirm the sizeable deviations found in the existing topographical maps and developed the general alternatives for the SHPP Nua.

 

What is WorldDEM?

Airbus WorldDEM is a homogeneous global digital elevation model. Its very high accuracy surpasses that of any satellite-based global elevation model available today. WorldDEM DTM is derived from WorldDEM and represents the bare terrain of the Earth’s surface.

Benefits

Designing a small hydroelectric power plant (SHPP) requires precise and reliable data to make the right decision and select the best option. The very high resolution and accuracy of WorldDEM DTM is a real asset to gain time and validate a ground survey topographical map. It is also necessary for hydro study and engineering/infrastructure design.

Through its reliable database, it is possible to identify and address any gaps in order to optimise the design and the energy production. DEMs can therefore be used as a double-check tool - to review, validate and update a first feasibility study and plan the concept.

  • Field investigations can be planned more effectively by determining potential areas in advance
  • Accurate estimation of the available head for better calculating the power potential
  • Proper evaluation of the hydropower feasibility demands estimation of various terrain parameters and flow characteristics provided by WorldDEM DTM
testimonials
Organisation Involved

Alternative reliable designs for the remotely located Nua Small Hydropower Plant needed to be developed with limited topographical information. WorldDEM served as the topographical data basis to review the existing study and to assess the area for possible design alternatives prior to field investigations. Plus, it estimated the hydraulic head for the evaluation of the energy production.

Logo TRACTEBEL Engie

Muhammad Ikhwan

Project Manager, Tractebel Hydroprojekt

Tractebel Engineering GmbH (formerly Lahmeyer International GmbH) is an international company, which offers a broad range of planning and consultancy services. Tractebel Hydroprojektis one entity of Lahmeyer International specialised in planning and design, and consulting in the field of hydraulic engineering. PT. PLN (Persero) is an Indonesian government-owned corporation in charge of the electricity distribution.

Want to know more?

Our sales team will be happy to provide you more information about this case study and how it can meet your business needs.

satellite-image-map-airbus-product-page.jpeg

See all our case studies

See all
RoyalBotanic_Madagascar_SPOT.jpg
Climate Risks and Disasters
Environmental Assessment and Prediction
WorldDEM™ Neo

Reforestation and Fire Management in Madagascar with WorldDEM™ Neo

Leveraging High-Resolution terrain data to enhance biodiversity conservation and community livelihoods in the massif d’Itremo protected area by the Royal Botanic Gardens

banner-barry Callebaut-deforestation-free cocoa-compliance.jpeg
Forestry and Environment
Pléiades

Starling backs Barry Callebaut for a deforestation-free cocoa supply chain

Starling provides satellite-based deforestation monitoring across Barry Callebaut`s entire cocoa supply chain to support their sustainability commitments.

Photo taken in a corn field underneath the plants
Agriculture
Pléiades Neo

Supporting transition towards Carbon Farming through monitoring and certification

Airbus joins the Horizon Europe project CAFAMORE to support the agricultural transition towards carbon farming. Together with its partners, Airbus will develop a robust and cost-effective system to measure soil carbon sequestration. Airbus will lay the groundwork for the CRCF, an EU-wide carbon market framework designed to financially incentivise farmers for sustainable practices.